CO129-342 - Governor Lugard & Public Offices - 1907 [11-12] — Page 279

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

17:081

124 909?

a edt as

ero JA

doung edd da drum ma

need bad dredg a bag

estidden damit eril

275

also been made to drive the bottom heading from a point in the cutting south of the tunnel, 480 ft. from the shaft and this had been driven about 40 ft. This heading is in decomposed granite and was so far offering no difficulties although rather heavily watered. The gullet in the approach cutting, also in decomposed granite, had reached the tunnel face and the heading into the tunnel was on the point of being started. Since December these headings had been extended and by the last mail were advancing about six feet per day.

Mr. Eves has been recommended to put down another shaft 270 ft. deep, 1,350 ft. from the north face. This will expedite the work by at least three months and will also facilitate the egress of spoil and ingress of building material which will be a very serious question when all the faces inside the tunnel are at work.

It is evident, however, that if the work is to be completed in say 3 to 3½ years an extremely large labour force will be required, the supply and transport of building material also must be carefully organized on a very large and complete scale, as when the tunnel work is in full operation, work will be going on at 16 faces at the same time and these must all be served by the two headings. Much of course depends on the nature of the material to be met with; a great deal will no doubt be composed granite with boulders but, there is little doubt that solid granite rock will also be found.

In view of what has been said, it is evident that the construction of the tunnel is a large and serious problem and will keep a large organizing staff busy besides necessitating the importation of an unusual amount of suitable labour. The most suitable would, as we have said, be probably drawn from the mining population in the vicinity of the Kaiping mines in North China, and this must be organized. The English tunnel foremen sent out have not turned out very satisfactorily and in various matters difficulties have occurred which are not infrequently...

-10-

zas.

Var

Edit History

2026-06-05 19:28:46 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
17:081 124 909? a edt as ero JA doung edd da drum ma need bad dredg a bag estidden damit eril 275 also been made to drive the bottom heading from a point in the cutting south of the tunnel, 480 ft. from the shaft and this had been driven about 40 ft. This heading is in decomposed granite and was so far offering no difficulties although rather heavily watered. The gullet in the approach cutting, also in decomposed granite, had reached the tunnel face and the heading into the tunnel was on the point of being started. Since December these headings had been extended and by the last mail were advancing about six feet per day. Mr. Eves has been recommended to put down another shaft 270 ft. deep, 1,350 ft. from the north face. This will expedite the work by at least three months and will also facilitate the egress of spoil and ingress of building material which will be a very serious question when all the faces inside the tunnel are at work. It is evident, however, that if the work is to be completed in say 3 to years an extremely large labour force will be required, the supply and transport of building material also must be carefully organized on a very large and complete scale, as when the tunnel work is in full operation, work will be going on at 16 faces at the same time and these must all be served by the two headings. Much of course depends on the nature of the material to be met with; a great deal will no doubt be composed granite with boulders but, there is little doubt that solid granite rock will also be found. In view of what has been said, it is evident that the construction of the tunnel is a large and serious problem and will keep a large organizing staff busy besides necessitating the importation of an unusual amount of suitable labour. The most suitable would, as we have said, be probably drawn from the mining population in the vicinity of the Kaiping mines in North China, and this must be organized. The English tunnel foremen sent out have not turned out very satisfactorily and in various matters difficulties have occurred which are not infrequently... -10- zas. Var
Baseline (Original)
1 2 17:081 124 909? a edt as ero JA doung edd da drum ma need bad dredg a bag estidden damit eril 275 also been made to drive the bottom heading from a point in the cutting south of the tunnel, 480 ft. from the shaft and this had been driven about 40 ft. This heading is in decomposed granite and was so far offering no difficulties although rather heavily watered. The gullet in the approach cutting, also in decomposed granite, had reached the tunnel face and the heading into the tunnel was on the point of being started. Since December these headings had been extended and by the last mail were advancing about six feet per day. Mr. Eves has been recommended to put down another shaft 270 ft. deep, 1,350 ft. from the north face. This will expedite the work by at least three months and will also facilitate the egress of spoil and ingress of building material which will be a very serious question when all the faces inside the tunnel are at work. It is evident, however, that if the work is to be completed in say 3 to 3 years an extremely large labour force will be required, the supply and transport of building material also must be carefully organized on a very large and complete scale, as when the tunnel work is in full operation, work will be going on at 16 faces at the same time and these must all be served by the two headings. Much of course depends on the nature of the material to be met with; a great deal will no doubt be composed granite with boulders but, there is little doubt that solid granite rock will also be found. In view of what has been said, it is evident that the construction of the tunnel is a large and serious problem and will keep a large organizing staff busy besides necessita- ting the importation of an unusual amount of suitable labour. The most suitable would as we have said be probably drawn from the mining population in the vicinity of the Kaiping mines in North China, and this must be organized. The English tunnel foremen sent out have not turned out very satisfactorily and in varibus matters difficulties have occured which are not, infrequently -10- zas. Var
2026-06-05 19:28:46 · Baseline
View content

1

2

17:081

124 909?

a edt as

ero JA

doung edd da drum ma

need bad dredg a bag

estidden damit eril

275

also been made to drive the bottom heading from a point in the cutting south of the tunnel, 480 ft. from the shaft and this had been driven about 40 ft. This heading is in decomposed granite and was so far offering no difficulties although rather heavily watered. The gullet in the approach cutting, also in decomposed granite, had reached the tunnel face and the heading into the tunnel was on the point of being started. Since December these headings had been extended and by the last mail were advancing about six feet per day.

Mr. Eves has been recommended to put down another shaft 270 ft. deep, 1,350 ft. from the north face. This will expedite the work by at least three months and will also facilitate the egress of spoil and ingress of building material which will be a

very serious question when all the faces inside the tunnel are

at work.

It is evident, however, that if the work is to be

completed in say 3 to 3 years an extremely large labour force

will be required, the supply and transport of building material

also must be carefully organized on a very large and complete

scale, as when the tunnel work is in full operation, work will

be going on at 16 faces at the same time and these must all be

served by the two headings. Much of course depends on the

nature of the material to be met with; a great deal will no

doubt be composed granite with boulders but, there is little

doubt that solid granite rock will also be found.

In view of what has been said, it is evident that the construction of the tunnel is a large and serious problem and will keep a large organizing staff busy besides necessita- ting the importation of an unusual amount of suitable labour. The most suitable would as we have said be probably drawn from the mining population in the vicinity of the Kaiping mines in North China, and this must be organized. The English tunnel foremen sent out have not turned out very satisfactorily and in varibus matters difficulties have occured which are not,

infrequently

-10-

zas.

Var

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.